A. Brine / saline-water system
- Boreholes where technically appropriate
- Pumps and brine-collection systems
- Channels and pipelines
- Storage and control structures
The project at a glance, what the survey work found, the resource figures, the borehole plan, the development concept — and the project information available to partners.
| Item | Detail |
|---|---|
| Project | Salt production & processing |
| Developer | Noolays Salt Producer Cooperative |
| Country | Ethiopia |
| Region | Somali Regional State |
| Zone | Nogob Zone |
| Woreda | Dihun Woreda |
| Kebele | Jajabe Kebele |
| Resource area | Habulay Saline River Basin |
| Development model | Pilot → Commercial → Industrial |
| Primary resource | Saline water / salt resource |
| Initial focus | Solar evaporation and raw-salt production |
| Long-term focus | Processing, refining, iodization, packaging and industrial products |
| Partnership sought | Investment + technology + engineering + markets |
The project sits on the Habulay saline river basin, where surface salt crusts and shallow saline groundwater occur naturally. The site provides the foundation for a solar-based salt-production operation, subject to detailed resource characterisation, engineering assessment, environmental requirements and commercial feasibility.
| Point | Detail |
|---|---|
| Resource area | Habulay Saline River Basin |
| Project location | Gansale Village (central point) |
Satellite imagery, site maps, boundary information and access information form part of the data room available to qualified partners.
Preliminary field work and remote-sensing analysis have been undertaken to understand salinity characteristics, brine occurrence, surface conditions, the geological setting, hydrogeological conditions, potential evaporation areas and site accessibility.
| Parameter | Value range | Interpretation |
|---|---|---|
| TDS | >250,000 mg/L | Hypersaline — suitable for commercial salt extraction |
| Na⁺ / Cl⁻ ratio | 0.9 – 1.1 | Near-marine composition |
| SO₄²⁻ content | High | Indicates gypsum and anhydrite dissolution |
| pH | 6.5 – 7.5 | Neutral to slightly saline |
| Evaporation rate | ≈7 – 9 mm/day | High potential for natural solar evaporation ponds |
The Habulay River area lies within the south-eastern Ethiopian plateau and is structurally part of the Ogaden Basin. The stratigraphic succession observed and confirmed by field and remote sensing studies includes:
| Geological period | Formation | Lithology | Salinity potential |
|---|---|---|---|
| Cretaceous | Korahe Formation (Kg1–Kg2) | Alternating gypsum, shale, limestone, anhydrite | High — principal evaporite sequence and source of salt brine |
| Cretaceous | Mustahil Formation (Km) | Marl, limestone, sandstone | Moderate — secondary salinity contribution |
| Cretaceous | Ferfer Formation (Kf) | Shale, dolomite, anhydrite | Moderate to high — contributes sulphate brine |
| Jurassic | Gabredarre & Agula Formations | Limestone and marl | Moderate — acts as aquifer host for saline circulation |
| Jurassic | Urandab & Antalo Formations | Shale, marl, limestone | Low — confining and structural support units |
| Component | Estimated coverage | Potential yield |
|---|---|---|
| Surface salt crusts | ≈2.5 km² | 20,000 – 25,000 tons (NaCl) |
| Shallow brine zone | 3 – 5 m depth | 45,000 – 60,000 m³ brine |
| Gypsum / anhydrite beds | 10 – 15 m thick | 500,000 – 700,000 tons (gypsum equivalent) |
15 – 20 ha of favourable evaporation-pond areas identified
>10 years at the planned abstraction rate (preliminary)
Remote sensing (satellite) and stratigraphic correlation with the Korahe Basin
The cooperative's concept map proposes five shallow exploration boreholes along the Habulay River corridor, inside an identified 150 ha permit area. Each location targets a different part of the brine system so that salinity and water chemistry can be compared between locations before the pilot evaporation ponds are designed.
| # | Location |
|---|---|
| 1 | Centre brine pool (main GPS) |
| 2 | Upstream wadi |
| 3 | Downstream wadi |
| 4 | East bank, mid-wadi |
| 5 | West bank, mid-wadi |
| Method | Note |
|---|---|
| Hand auger / manual drilling | Suitable for the first 10 m in soft sediments; low cost. |
| Small rotary rig | 10–25 m depth with PVC casing and screen at the bottom. Recommended as the main method. |
| Monitoring-well completion | Casing, screen and gravel pack for repeated sampling and water-level monitoring. |
≈150 ha identified permit area · 5 shallow exploration boreholes (15–25 m depth) · Brine confirmation for a 10,000–25,000 t/year concept
The proposed technical development combines several interconnected systems. The final configuration will follow engineering studies, resource confirmation and economic analysis.
Refined and iodized salt for human consumption, subject to applicable Ethiopian standards, laboratory testing, certification and regulatory requirements.
Salt for industrial customers requiring specific purity, particle size and chemical specifications.
Products developed for livestock applications according to appropriate technical and regulatory requirements.
Bulk raw salt for customers with suitable processing capacity.
Additional products may be considered after technical and market validation.
Subject to confidentiality and the nature of the request, the investor information package can include:
Technical data disclaimer — how we describe these preliminary figures (PDF)
A potential investor may conduct or commission any of the following, and Noolays will cooperate with the process.
Corporate and contractual review.
Land documentation, site handover and permits.
Resource, engineering and hydrogeology.
Sampling, brine and product analysis.
Environmental studies and management measures.
Pond design, pumping, processing configuration.
Product specifications, customers, logistics.
Capital and operating cost assumptions.
Structure, milestones and agreements.
Contact for project information: Abdifatah Hussein — [email protected] / +251 921 650 347